291 patients moved to new Amphia hospital

291 patients were safely transferred to their rooms in the new hospital on Molengracht in Breda on Friday 29 November 2019. The patient move got under way at 8:00 this morning. Emergency care also opened at the new site at the same time. Patients were moved from two locations: from Langendijk in specially equipped medical transport, and from the existing Molengracht building through the brand-new underground corridor. Soon after the move began, the first patient, 1.5-year-old Floor, arrived at the new hospital with her father.
By around 17:00, all patients were in their new single rooms and the inpatient wards in the new building were operational. The new Emergency Department, GP out-of-hours centre and maternity services are also now up and running. A further move was scheduled for 30 November, involving the outpatient clinics. The outpatient clinics at the new hospital open on Monday 2 December. Amphia is delighted that the first babies have already been born at the new hospital.

A special day for the paediatric ward
Particular attention was paid to all the children and infants moving from Langendijk to Molengracht today. The special transport was decorated with colouring sheets the children had been able to make themselves beforehand. A warm welcome awaited them in their new rooms, with teddy bears and CliniClowns.
The first baby was born at the new site at 11:00. At Langendijk, we said goodbye to a long-standing tradition of births. The last baby was born there at 08:10. Both babies are doing well.
Moving with a smile
The long and meticulous preparations paid off today. Amphia staff enthusiastically helped with the move. Everyone’s first priority was to ensure the patients were moved safely. But boxes and wheeled containers were also moving back and forth all day. Spirits were high, and the move was carried out with pride and a smile.
Good cooperation with care partners
As well as children, there were also older people who had to swap their old room for a new one. We wanted to avoid moving particularly vulnerable older people, who needed follow-up care in a nursing home, for example, twice within a short period. At Amphia’s request, various care partners waived waiting times and temporarily made extra capacity available for around 20 patients.
Question about this story? Ask your question
Wie aan Amphia Ziekenhuis Breda Molengracht werkte
- Erwin Kersten (Van Wijnen)Van WijnenMentioned in Keys handed over as new Amphia hypermodern hospital is completed after three years of construction
- consortiumTrebbeMentioned in Keys handed over as new Amphia hypermodern hospital is completed after three years of construction
- consortiumENGIE ServicesMentioned in Keys handed over as new Amphia hypermodern hospital is completed after three years of construction
- Construction consortiumFourCareMentioned in Keys handed over as new Amphia hypermodern hospital is completed after three years of construction
- construction partner
UnicaMentioned in Breda, Amphia Hospital | Amphia construction team: ‘Integrated bespoke solutions, thinking in 3D’ - clientAmphiaMentioned in Breda, Amphia Hospital | Amphia construction team: ‘Integrated bespoke solutions, thinking in 3D’
- architectWiegerinck architectuur en stedenbouwMentioned in Breda, Amphia Hospital | Amphia construction team: ‘Integrated bespoke solutions, thinking in 3D’
- P&L deurconceptenLimburgia & PolvoMentioned in Breda, Amphia Hospital | Door closers to operating theatre standard
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAmphia Ziekenhuis Breda Molengracht
- ThemeHospital construction and refurbishment
- SubjectGeneral