Breda, Amphia Hospital | Amphia construction team: ‘Integrated bespoke solutions, thinking in 3D’

Breda, Amphia Hospital | Amphia construction team: ‘Integrated bespoke solutions, thinking in 3D’

Designing and building an 80,000 m² hospital complex that is fit for the future is possible when partners work together on key aspects, say the construction partners behind Amphia’s new building in Breda, which opened in November. To achieve this, the hospital’s brief was specified in an integrated contract, delivered by the FourCare consortium (Trebbe, Van Wijnen, ENGIE Services and Unica). The builders and technical services providers were equal partners. Amphia construction director Jasper Meijer: “The consortium did not want to make money from variations, but from a good process.”

What was Amphia’s objective in 2008, when the new-build programme began?

Meijer: “To create a multidisciplinary tertiary teaching hospital for the south-west Netherlands on a single site, by bringing together two hospital sites in Breda. A site was eventually found on a car park and football complex south of the existing Molengracht hospital. We want to concentrate highly complex care on one site in the interests of safety and efficiency.”

Hergebruikt mozaïek.

Handover of the keys to the new Amphia. The state-of-the-art hospital was completed after three years of construction. From left: Erwin Kersten (Van Wijnen), Hein Trebbe sr. (Trebbe), Peter Smeets (Engie Services), William Swinkels (Unica), Frank Brekelmans (FourCare), Jasper Meijer, Roos Leber, Remco Djamin and Olof Suttorp (all Amphia).

A consultation and design process of this kind takes a great deal of time. Healthcare accommodation adviser ptg advies has been involved since the vision was being developed.

Michiel Sitsen, partner and adviser at ptg advies: “The building is being designed for a lifespan of around 40 years. A future-proof vision and an accommodation strategy are needed to ensure that it is built with this in mind. Based on Amphia’s vision, we developed an accommodation strategy for Amphia’s sites with the hospital organisation. We then agreed the principles with Amphia and developed them into a Schedule of Accommodation. Working with the designers, we went on to develop the masterplan, oversee the further development of the designs, and manage the process and project. We also advised on the financial control of the new-build project and supported financial management. Together with Amphia, we contributed to the municipality’s spatial planning process, both substantively and procedurally.”

Meijer: “The collaboration with the municipality should certainly not be underestimated. This is also, of course, an urban planning project. The volume of the new-build programme even doubled after the site was moved to the other side of the existing hospital. The Langendijk site will eventually close once the refurbishment of the existing hospital is complete, which is expected by the end of 2021. That means 10 years of design and 2.5 years of construction.”

Wouter Bezemer, algemeen directeur van Huybregts Relou.

Jasper Meijer (Amphia): ‘We want to concentrate highly complex care on one site in the interests of safety and efficiency.’

The spaces in the new hospital have been designed to be as ‘universal’ as possible, making them easy to operate both now and in the future. How do you make an 80,000 m² building flexible enough for the future?

Herman Dik, project manager at Deerns: “Generally speaking, the space required for building services increases over the years, and the design needs to take this into account. In the new Amphia hospital, 13 to 14% of the volume has been allocated to building services. The new building has high ceilings throughout, but we certainly haven’t over-dimensioned it. The design provides a high level of finish while remaining both flexible and reliable during the operational phase.”

Gerard van Boxtel, representing ENGIE Services in FourCare: “As part of optimising the new-build design, for example, the plant rooms on each floor were eliminated and centralised. The main building services are located on the top floor of the new building, including IT. Sustainability was also a major focus. The sustainable energy concept is based on low-temperature heating and high-temperature cooling. To this end, 6 thermal energy storage wells were drilled. Two heat pumps are located in 2 building sections, supported by heat recovery systems on the air handling units. This reduces CO2 emissions by 80%. Climate ceilings and LED lighting have also been installed throughout.”

Herman Dik (Deerns): ‘The tender phase ensured that the client would get the building it had asked for.’

Hospital architecture means planning for the future. How was this concept approached?

Jarno Nillesen (Wiegerinck architectuur en stedenbouw): “A hospital needs a structure that supports today’s care logistics and is flexible enough to expand or contract. At its heart is the intervention building, which houses the emergency department, intensive care, GP out-of-hours service and operating theatre centre. Around it are three other buildings for Women, Mother and Child, Oncology, and Heart & Vessels. The intervention building is a dynamic area over the hospital’s lifetime, and has been positioned and designed so that it can be adapted easily when needed. Architecturally, we created an ensemble of buildings on a human scale. The building’s mass is divided into equally sized sections with plenty of daylight, each with an internal courtyard and a clear, individual identity.”

Key parts of the building were designed using 3D BIM. How does this work in practice?

Nillesen: “Designing in a digital environment means everyone is talking about the same thing and can truly understand one another. Paper is 2D, but we think in 3D. It was even possible to walk through the future hospital environment wearing a VR headset.”

Jasper van der Meer, construction project leader on behalf of FourCare: “We used BIM throughout for the main components and aligned our meeting structures accordingly. We did not develop the 3D models down to every last detail, such as the skirting boards in the meeting room. Details like that make the models unnecessarily heavy and therefore impractical to work with.”

Jan-Martien Touw, property and technical services manager at Amphia: “That would also have made the design process unnecessarily expensive. BIM certainly proved its worth during construction. A digital environment also makes it possible to code components effectively, so the design can be traced during the operational phase. We achieved this successfully through integrated collaboration between the design and construction teams.”

How did Amphia take the design through to contract formation?

Meijer: “We wanted the builder and technical services provider to be equal partners and to share responsibility for engineering and delivery. We then developed our own version of UAV-gc (no bill of quantities, but functional specifications; ed.) and tested it against the market, more specifically with five consortia, of which two ultimately remained.”      

Dik: “The final candidates were asked to study a specific building section against clear objectives: the construction consortium had to show that the design could be built and propose solutions. This ensures that the client really does get the building it asked for.”

Familie en dierbaren kunnen in alle omstandigheden veilig contact hebben met de patiënt.

Gerard van Boxtel (FourCare): ‘The design process for the refurbishment is in full swing.’

The FourCare consortium ultimately offered the best approach at the best price. Arjan van Haperen (Unica), Gerard van Boxtel (ENGIE Services), Hein Trebbe (Trebbe Bouw) and Jasper van der Meer (Van Wijnen) on the project:

Trebbe: “The way the teams worked together at Amphia is a model for hospital construction. Given the scale and the need to spread risk, several parties were needed, but they also genuinely worked as an integrated team. All the parties, including the client, shared one site cabin. The collaboration within FourCare, with the right people in the right roles, was excellent and is continuing on projects for other clients. There is a great deal of mutual respect.”

Van Boxtel: “There was no division of responsibilities between the consortium partners, nor was there a traditional distinction between electrical and mechanical services.”

Van Haperen: “Integrated collaboration enables you to work efficiently. Speed of construction was, of course, important. The construction and building services work was coordinated from the outset to prevent issues during delivery. Much of the work was prefabricated, and the fit-out and shell construction processes were also integrated. For example, the sanitaryware frames were installed during the shell construction phase.”

Van der Meer: “With a tight schedule, we worked from the ‘rough’ to the ‘fine’. That made the desired construction period of 32 months both plannable and achievable. The first building section was practically complete by summer 2018, which showed us we were on track. It did, however, require flawless planning, with the tower cranes in continuous use. At one point, 600 people were working on site. We built a completely new 80,000 m² hospital on time and within budget, with an average shell construction output of 750 m² per day.”

De ‘normale stand’. Het ziekenhuis kent een duidelijke scheiding van hotfloor en (poli)klinieken en kantoor. Functies zijn zo gepositioneerd dat looplijnen/stromen helder zijn.

The planned construction period was met exactly, with around 100 outstanding items in total when the keys were handed over at the end of spring 2019. That is very few for a project of this scale.

Meijer: “In terms of scale, you could compare this project with 400 family homes. A construction consortium that focuses on solutions deserves understanding. Transparent communication also allows the contractor to keep production moving. We agreed with the consortium’s position: ‘we don’t want to make money from variations, but from a good process’. It paid off, because together we were able to stay ahead of issues.”

Van Haperen: “That is important, for example, in so-called ‘hold areas’, where parts of the work are carried out later because they still need to be specified in more detail. We were able to come together at key moments.”      

De ‘crisisstand’. Een deel van het ziekenhuis wordt snel omgeschakeld, met een gesloten geïnfecteerd circuit en een noodhospitaal. De reguliere zorg kan ongehinderd doordraaien.

Amphia has delivered a highly sustainable hospital (EPC <1), and FourCare has now also begun refurbishing the existing 35,000 m² hospital. It is conceivable that the predicted surplus heat from the new building could be used to supply energy to the existing building.

Touw: “Certainly, but that is still at an exploratory stage.”

Van Boxtel: “The design process is in full swing. We are working on it.”

Meijer: “For the refurbishment, we chose FourCare’s established team, based on its proven collaboration. This will ensure that the best possible result is delivered: a sustainable, multidisciplinary tertiary teaching hospital.” 

Key facts: new Amphia building

• 80,000 m² of new-build space for 4,500 staff

• An integrated team of contractors and building services specialists (under UAV-gc)

• 572 single rooms, each with its own bathroom

• 16 operating theatres, including 2 hybrid operating theatres

• Car park with 900 spaces

• Thermal energy storage based on 6 wells, supported by heat recovery on air handling units (EPC < 1; 80% reduction in CO2 emissions)

A business enquiry for Unica? Get in touch

Who worked on Amphia Ziekenhuis Breda Molengracht

  1. architectureWiegerinck architectuurMentioned in New-build Amphia Hospital Breda
  2. housingPTG AdviesMentioned in New-build Amphia Hospital Breda
  3. technical mattersDeernsMentioned in New-build Amphia Hospital Breda
  4. constructionABTMentioned in New-build Amphia Hospital Breda
  5. landscapeBosch & SlabbersMentioned in New-build Amphia Hospital Breda
  6. integrated consultancyPieterse terwel grevinkMentioned in New-build Amphia Hospital Breda
  7. Erwin Kersten (Van Wijnen)Van WijnenMentioned in Keys handed over as new Amphia hypermodern hospital is completed after three years of construction
  8. consortiumENGIE ServicesMentioned in Keys handed over as new Amphia hypermodern hospital is completed after three years of construction
  9. Construction consortiumFourCareMentioned in Keys handed over as new Amphia hypermodern hospital is completed after three years of construction
  10. construction partnerUnicaIn this story
  11. clientAmphiaIn this story
  12. architectWiegerinck architectuur en stedenbouwIn this story
  13. door closersGEZEMentioned in Breda, Amphia Hospital | Door closers to operating theatre standard
  14. P&L deurconceptenLimburgia & PolvoMentioned in Breda, Amphia Hospital | Door closers to operating theatre standard
  15. architectWiegerinckMentioned in Breda, Amphia Hospital | Door closers to operating theatre standard

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAmphia Ziekenhuis Breda Molengracht
  • ThemeHospital construction and refurbishment
  • SubjectInteriors
  • CompanyUnica
  • CompanyAmphia
  • CompanyWiegerinck architectuur en stedenbouw